(a) the details of present status of on-going railway projects/surveys in Maharashtra;
(b) the expenditure incurred on each project till date; and
(c) the time by which these projects are likely to be completed ?
(a) the details of present status of on-going railway projects/surveys in Maharashtra;
(b) the expenditure incurred on each project till date; and
(c) the time by which these projects are likely to be completed ?
MINISTER OF STATE IN THE MINISTRY OF RAILWAYS (SHRI DIGVIJAY SINGH )
(a) to (c) : The present status of on-going railway
projects/surveys in Maharashtra, including their anticipated
cost, expected expenditure likely to be incurred till March
2001, outlay for 2001-02 and targets wherever fixed are at
Appendix-I. Details of on-going surveys in Maharashtra are
at Appendix-II.
Appendix-I
APPENDIX REFERRED TO IN REPLY TO PARTS (a) TO (c ) OF LOK SABHA
UNSTARRED QUESTION NO. 4993 FOR 19.4.2001
S. Name of Latest Outlay Budget Status No. Project Anticip-expecte Outlay ated d to Proposed Cost end of for 2001- 2000-01 02
(Amount in Crores of Rupees)
ON-GOING RAILWAY PROJECTS IN MAHARASHTRA
New Lines
1 Amravati- 175.30 39.58 8.00 Land acquisition in 6 Narkher villages out of 72 villeges have been completed. Earthwork and bridges for 18 section out of 27 has been taken up and work is in progress . Contracts for 9 major bridges have been awarded. Building work of Amrawati station building is nearing completion. Work is being progressed as per availability of resources. 2 Ahmednagar- 353.08 3.46 3.00 Final location survey has been Beed-Parli completed for 15 km from Vaijnath Ahmednagar end . Land acquisition plans & papers have been submitted to the State Govt. for this length. The work would be progressed once the land becomes available. Station building at Beed is also in progress. 3 Panvel- 106.90 34.38 14.00 All land except 10.64 hect. Karjat : forest land has been Electrified acquired. Land acquisition Line (Phase- process for forest land is in I) progress. Earth work in 7 sections out of 9 is in good progress where 79% progress have been achieved,Work on 2 out of 9 major bridges and 19 out of 39 minor bridges have been completed. Work on the
2.7 km long tunnel is in good progress. Work is being progressed as per availability of resources. 4 Baramati- 75.00 0.10 4.00 Final location survey has been Lonad taken up and is expected to be completed shortly.This will be followed by preparation of land acquisition plans and papers. 5 Puntamba- 32.00 1.00 4.00 Final location survey has Shirdi been completed. Land acquisition is being taken up.
Gauge Conversion
6 Miraj-Latur 329.02 105.30 20.00 The work is being progressed in phases. In the first phase, Gauge conversion work from Kuruduwadi to Pandharpur (52 km) has been completed . Residual works in the section are in progress. On Latur Road- Latur (42 km) earthwork and major and minor bridges have been completed. Ballast collection is nearing completion. Work on Kurduwadi- Latur (143 km) is in progress between Khurduwadi and Yedshi
(113 km) section. No work on Osmanabad diversion (30 km ) has been takenup. Miraj Pandharpur (137 km) ph IV work will be taken up as last phase of the project. Work is being progressed as per availability of reslources. 7 Mudkhed- 170.51 37.60 20.00 The work has been taken up Adilabad under BOLT scheme .Agency has not been able to progress the work of late due to financing problem. In case finance is made available project is expected to be completed in 18 months time. 8 Solapur- 265.77 130.04 10.00 The work is being done in Gadag phases. The work Solapur-Hotgi and Hotgi to Bijapur has been completed. Work is in progress on rest of section from Bijapur to Gadag which will be completed in the coming years as per availability of resources.Financial participation of Government of Karnataka in the project is being tried with a view to expedite early completion of this work. 9 Secunderaba 287.83 35.00 19.87 The work has been taken up in d-Mudkhed first phase from Mudkhed- & Nizamabad(96 Km). Supply of Jankhampet- ballast 1,50,650cum out of Bodhan 2,34,000 cum has been collected at site. On Mudkhed- Nizamabad in seven reaches earth work has been completed and in balance 13 reaches works are in progress. Work has also been taken up in the remaining sections. The possibility of getting private funding for part of the work is being explored, with a view of expediting its completion. 10 Akola-Purna 228.00 10.00 10.00 Final Location Survey is in progress. Arrangements are being made to take up earthwork and bridges in first section from Purna to Hingoli
(95 km) . 11 Gondia- 242.82 242.32 0.10 The work has been completed. Chandafort Funds required for financial adjustments.
Doubling
12 Daund- 45.50 40.00 5.00 The work is in good progress Bigwan where earthwork and bridges have been completed and linking is in progress and expected to be completed during 2001-02. 13 Diva-Vasai 142.00 120.71 20.00 In phase-I , 11 km from Vasai Rd. to Kaman has been commissioned and 17 Km from Kaman to Bhiwandi has been completed. Bhiwandi to Diva is in progress where earthwork and bridges have been taken up. The work will be completed during 2001-02. 14 Panvel-Roha- 4.10 3.10 0.10 Final Location Survey Land completed. Land acquisition is acquisition in progress and is likely to be acquired shortly. 15 Diva- 49.00 7.00 13.00 Earthwork and Bridges in Diva- Kaylan Dombivali and Dombivali-Kaylan doubling of are being taken up. Plans are 5&6 line under approval. 16 Panvel- 48.00 1.00 1.00 Final location survey has been Jasai- completed. Detailed planning Jawaharlal has been taken up. Nehru Port Trust
(JNPT)
Metropolitan Transport Projects
17 Kurla-Thane 95.00 59.76 10.00 Work of earthwork, supply of 5th & 6th Ballast, Track linking, Major line (Phase- Bridges, Foundation and I) erection of OHE structures and other works are in progress in stretches which are free from encroachments. 18 Thane- 131.47 83.14 10.00 Civil works for second line Turbhe- are nearing completion. Nerul/ Electrification and signaling Vashi part works are in progress. Delay of corridor in acquisition of land is No.1 in affecting the progress of Navi Mumbai work. 19 Belapur- 92.50 82.38 8.00 Double line has been Panvel commissioned and opened for Doubling commuter traffic on 14-4- 2000.Balance works to be executed by CIDCO are in progress. 20 Belapur- 163.49 20.99 21.40 Work of important bridge on Seawood- Panvel creek ,construction of Uran : minor bridges ,sub way at Electrified Seawood and work at Sanpada line carshed are in progress. Due to financial crunch being faced by CIDCO, execution of the project has been divided in two phases. Under first phase single line will be laid in the section. 21 Kurla-thane 56.79 20.24 10.00 Earthwork, supply of Ballast, 5th and 6th Bridges and 22 kV aerial line feeder obstructing 5th and 6th
(Bhandup to line by underground cable Thane) between Bhandup- Mulund and Phase-II Mulund-Thane section is in progress. 22 Thane- 49.34 0.09 7.00 Work has been included in the Mumbra 5th Budget 2000-01 subject to and 6th clearances. Detailed survey line report is beng processed for submission to Planning Commission for their appraisal. 23 Borivali- 401.66 64.56 40.00 Work for earth work, major & Virar : minor bridges yard remodelling Quadrupling and quarters is in progress. 24 Santacruz- 87.89 82.42 5.00 Work on all minor and major Borivali : bridges have been completed. 5th line Work which was held up at certain locations due to delay in removal of encroachment, has been restarted. Borivali- Andheri section has already been commissioned. 25 Virar- 39.19 14.65 17.50 Signalling works completed. Dahanu Road Ancillary works in progress. : Autoblock Signalling 26 Virar 25.82 0.01 0.10 Work has been included in the Dahanu Road budget of 2000-2001 subject to - necessary clearances. Process Development for obtaining clearances has of been initiated. facilities for introductio n of EMUs and terminal facilities at Dahanu Road
Railway Electrification
27 Udhna- 138.13 59.16 15.31 Target is March 2003. Jalgaon
S. Name of the Project Plan head Status No.
1 Rotegaon-Punthamba New Line Survey is in progress. 2 Wardha-Pusad-Nanded New Line Survey is in progress. 3 Solapur-Tuljapur- New Line Survey is in Osmanabad progress. 4 Chinchwad and Roha New Line Not yet taken up. 5 Shirpur-Mhow New Line Survey is in progress. 6 Pune and Nasik New Line Survey is in progress. 7 Khandwa to Nardana via New Line Survey is in Khargone, Sendhwa progress. 8 Jalna-Khamgaon New Line Survey is in progress. 9 Pulgaon-Arvi GC with Gauge Survey is in extn. to Amla Conversion progress. 10 Pune-Lonavla Doubling Survey is in Quadrupling progress. 11 Daund â Manmad Doubling Survey is in progress. 12 Kalyan_Kasara 3rd line. Doubling Survey is in progress. 13 Daund-Bigwan-Gulbarga Doubling Survey is in progress. 14 Umrer to Nagpur via New Line Survey is in Khaperkheda and Koradi progress. 15 Ramtek to Gotegaon via New Line Survey is in Khawasa, Seoni and progress. Dhuma 16 Umrer to Nagbhir Gauge Survey is in Conversion progress. 17 Chhindwara-Nainpur Gauge Survey is in Conversion progress. 18 Naghbir to Nagpur Gauge Survey is in Conversion progress. 19 Chhindwara â Nagpur Gauge Survey is in Conversion progress. 20 Mumbai Central-Boravali Doubling Survey is in progress. 21 Dahanu Road â Nashik New Line Survey is in Road progress.