MINISTER OF STATE IN THE MINISTRY OF RAILWAYS ( SHRI R. VELU)
(a): The present status of construction of on-going Road Over
Bridges in Tamil Nadu is as under:- These Road Over/Under Bridges
are in various stages of planning and execution.
Status of work Cost Deposit Undergauge sharing terms conversion basis
Total sanctioned works 46 7 12
Works completed on Railway portion
but approaches not completed by
State Government 9 3 -
Works completed on approaches by
State Government but Railway
portion not completed by Railway 4 - -
Programmed for completion during 2005-06 6 4 2
(b): No, Sir.
(c): Does not arise.
(d): Railways construct Road Over/Under Bridges in lieu of existing
level crossings on cost sharing basis if the traffic density at the
level crossings reaches at one lakh TVUs (TVU - A unit obtained by
multiplying the number of trains with the number of road vehicles
passing over the level crossing in 24 hours) or more; otherwise on
deposit terms. Proposals in both conditions have to be sponsored
by State Government duly fulfilling certain preliminary pre-
requisites required under extant rules. No firm proposal has yet
been received from the State Government to construct Road Over
Bridges at `Manapparai`.