MINISTER OF THE STATE IN THE MINISTRY OF RAILWAYS
(SHRI R. VELU)
(a)&(d): Updating survey for new line from Bhanupalii-Beri via Bilaspur (63 kms.) was earlier
carried out in 1994-95. In the budget 2004-05, updating survey for new line from Bhanupalli-
Bilaspur was included. This has been completed in. February, 2005, As per updated survey
report, the cost of 47.65 kms. long line has been assessed at Rs. 641.48 crore with a rate
of return as (-) 20.93%. Zonal Railway has been advised to update the survey upto Beri as
was done in 1994-95. Updating survey for new line from Bhanupalli-Beri via Bilaspur (63 kms.)
is targeted for completion by 31.03.2006.
(b)&(c): Do not arise.