Question : NUCLEAR POWER PROJECT



(a) the names of the countries with which agreements have been signed for setting up of nuclear power plants in the country after the approval of international community alongwith the locations identified for these plants including their capacity to generate power; and

(b) the time by which these nuclear power plants are likely to commence the production?

Answer given by the minister


THE MINISTER OF STATE FOR SCIENCE & TECHNOLOGY AND EARTH SCIENCES (INDEPENDENT CHARGE), PMO,PERSONNEL, PUBLIC GRIEVANCES AND PENSIONS AND PARLIAMENTARY AFFAIRS (SHRI PRITHVIRAJ CHAVAN)

(a) Consequent to the clearance of the Nuclear Suppliers Group (NSG), enabling intergovernmental agreements (IGA) outlining the framework of cooperation including setting up nuelear power reactors have been signed with Russian Federation, France and the USA. Commercial agreements for setting up of reactors are presently under discussion. The government has accorded `in principle` approval of sites for setting up reactors in cooperation with foreign countries as follows:


Country Sites Designated Nominal Capacity (MW)
Russian Kudankulam,Tamilnadu 4x1000# Federation Haripur,West Bengal 6x1000
France Jaitapur,Maharashtra 6X1650
United States Kovvada,Andhra Pradesh 6x1000 of America Chhaya Mithi Virdi,Gujarat 6x1000

# Additional capacity, 2 x 1000 MW capacity is already under construction at the site.

(b) Pre-project activities are currently in progress at`these Sites. The planning is to start work on the first set of twin units at the above sites in 2012 subject to land acquisition. The commercial generation!;will start after 6 years from the first pour of concrete.