Question : Construction of PFBR

(a) the status of construction of the Prototype Fast Breeder Reactor (PFBR);

(b) the budgetary provisions made, funds released and utilized since its sanctioning in 2003; and

(c) the time by which it is likely to be constructed?

Answer given by the minister

THE MINISTER OF STATE FOR PERSONNEL, PUBLIC GRIEVANCES & PENSIONS AND PRIME MINISTER’S OFFICE (DR.JITENDRA SINGH):

(a) Bharatiya Nabhikiya Vidyut Nigam Ltd (BHAVINI), a CPSE under Department of Atomic Energy is constructing 500 MWe Prototype Fast Breeder Reactor (PFBR) at Kalpakkam, Tamil Nadu. Integrated Commissioning of PFBR is currently under progress.

(b)
Particulars Equity Loan Total
Rs. in cr Rs. in cr Rs. in cr
Budgetary provisions made 4314.52 1000.00 5314.52
since 2003

Funds released since 2003 4314.52 1000.00 5314.52
Funds utilised since 2003 4314.52 1000.00 5314.52

In addition to the above, Rs. 227.08 crore towards Equity from Nuclear Power
Corporation of India Limited has also been utilised fully.
Cumulative expenditure as on 31.12.2020 is Rs. 5850 crore which is inclusive
of short term interest earned and loan from State Bank of India (SBI).

(c) PFBR is expected to become operational by October 2022.

*****