Question : DEVELOPMENT PROJECTS IN NER



(a) the details of the funds allocated/utilized for the projects/schemes being implemented in the North Eastern Region (NER) during each of the last three years and the current year;

(b) whether the Government has conducted any survey to identify the areas for implementing the development projects/schemes in the North Eastern Region;

(c) if so, the details thereof;

(d) the details of the projects sanctioned and completed during the said period, and

(e) the steps being taken by the Government to ensure proper and timely utilization of funds earmarked for the development projects in the North Eastern Region?

Answer given by the minister


MINISTER OF STATE (INDEPENDENT CHARGE) IN MINISTRY OF DEVELOPMENT OF NORTH EASTERN REGION (SHRI PABAN SINGH GHATOWAR)

(a) The details of the funds allocated/utilized for the projects/schemes being implemented under Non-Lapsable Central Pool of Resources (NLCPR) scheme and schemes of North Eastern Council of this Ministry in the North Eastern Region (NER) during each of the last three years and the current year are given below :-

(Rs. in crore)
Scheme	Funds	2010-11	2011-12	2012-13	2013-14	allocated/utilized	(up to 31.01.2014)
NLCPR	Funds allocated	805.77	798.99	775.00	948.00	Funds utilized	805.77	798.99	775.00	630.21
NEC	Funds allocated	700.00	700.00	770.00	700.00	Funds utilized	678.83	693.18	732.76	557.57
(b) and (c) Infrastructural constraints being faced in the development of NER has been assessed in the `North Eastern Region Vision 2020` document. Further, projects/ schemes under NLCPR and NEC Schemes are considered as per the priority list of projects submitted by the North-Eastern States, which are based on infrastructural gaps in the region.

(d) The details of the projects sanctioned and completed during the said period are given below:-
Scheme	Projects	2010-11	2011-12	2012-13	2013-14	sanctioned/completed	(up to 31.01.2014}
NLCPR	Projects sanctioned	150	106	81	72	Projects completed	49	36	56	36
NEC	Projects sanctioned	107	122	109	30	Projects completed	24	20	48	13
(e) To ensure proper and timely utilization of funds, projects are monitored on a regular basis through quarterly progress reports Review meetings are also held from time to time besides field visits and third party monitoring. Utilization Certificate for released funds are also insisted upon before release of second and subsequent instalments.