Question : FOUR LANING OF NH-3



(a) whether a proposal for four laning of NH-3 from Wadape-Gonde to Dhulia has been pending for final approval of the Union Government;

(b) if so, the details thereof and reasons therefor; (

(c) whether environmental and other related clearance thereto was accorded subject to the certain conditions two years ago has been held up extraneous considerations;

(d) if so, the details thereof alongwith steps being taken to sort out of the same;

(e) whether the project is intended to be implemented under the B.O.T. system; and

(f) if so, the name of the interested parties?

Answer given by the minister


THE MINISTER OF STATE IN THE MINISTRY OF SHIPPING, ROAD TRANSPORT AND HIGHWAYS (SHRI K.H. MUNIYAPPA)

(a) & (b) Four laning of Vadape-Dhule Section of NH-3 has been approved under National Highway Development Programme (NHDP) Phase-III on Build Operate and Transfer (BOT) basis. Vadape-Gonde & Pimpalgaon-Dhule Section has been approved for four laning under NHDP Phase IIIA and the work has been awarded for implementation of four laning on B.O.T. basis. Gonde Nashik-Pimpalgaon Section of NH-3 has been approved for four laning under NHDP Phase-IIIB and the preparation of Detailed Project Report (DPR) has been taken up.

(c) & (d) The environmental clearance for Dhule – Pimpalgaon Section has been approved by Ministry of Environment & Forests and that for Vadape-Gonde Section has been taken up. The environmental clearance for Gonde-Nashik-Pimpalgaon Section shall be taken up after the preparation of DPR is completed.

(e) & (f) The projects have been taken up on Build Operate and Transfer (BOT) basis. The Vadape-Gonde Section (length 100 Km) has been awarded to M/s Gammon-Sadbhav Billmoria (JV) and Pimpalgaon-Dhule Section (Length 118 Km.) is awarded to M/s IRCON SOMA JV.