Question : Construction of New Rail Lines in Bihar

(a) whether the Government has allocated funds for the construction of new railway line in Bihar as declared in the year 2014 by the railways;

(b) if so, the details of the funds allocated for the purpose; and

(c) the time limit fixed to complete the construction work of new railway line between Sultanganj-Katoria and Bariarpur-Mananpur?

Answer given by the minister

MINISTER OF STATE IN THE MINISTRY OF RAILWAYS

(SHRI RAJEN GOHAIN)


(a) and (b): No new line falling fully/partly in Bihar was included in Railway Budget 2014-15.

(c): Both Bariarpur-Mananpur (69 km) new line and Sultanganj-Katuria (76.5 Km) new line projects were included in 2007-08. Final Location Surveys for both these projects have been completed. Completion of project depends upon several factors including complete handing over of encumbrance-free land by the State Government, statutory clearances, shifting of utilities, etc. Since issue of land acquisition is beyond the control of Ministry of Railways, no time-frame has been fixed for completion of these projects.
*****