MINISTER OF STATE IN THE MINISTRY OF RAILWAYS (SHRI DIGVIJAY SINGH)
(a): Yes Sir, however, replacement of mechanical weighbridges is only on condition basis.
(b) & (c) 39 electronic in-motion weighbridges have been ordered. At 14 locations these have been commissioned and for the balance, matter is under process. Details are furnished in the Appendix.
(d) The funds required for 39 weighbridges ordered are approximately Rs. 3.5 crores.
APPENDIX
Appendix to the Lok Sabha Unstarred Question No. 2842 for 15.03.2001
I) Weighbridges already commissioned
S.NO. RAILWAY LOCATION
1. Central Jhansi +
2. Hotgi
3. Eastern Andal
4. Andal
5. Northern Chanheti
6. North East Frontier Jogigopha
7 Rangapani
8. Southern Perambur +
9. Royapuram
10. South Central Guntakal
11. Guntapalli +
12. South Eastern Kharagpur
13. Champa
14. Western Viramgram
II) Locations where work is in progress:-
S.No. Railway Locations
1. Central Jhansi
2. Nagpur
3. Eastern Jamalpur +
4. Dhanbad
5. Northern Jagadhari +
6. Juhi
7 Merta Road
8. Bhatinda
9. North East Frontier Rangiya
10. Southern Ernakulam
11. Attippattu
12. Chengalpatu
13. Melapakkam
14. South Central Bhanapur
15. South Eastern Raipur +
16. Bimalgarh
17. Hindol Road
18. Amlai
19. Waltair
20. Muri
21. Marauda
22. Dangoaposi
23. Western Udhna
24. Jamnagar
25. Sawai Madhopur