Question : BY PASS ON NATIONAL HIGHWAY NO. 7



(a) whether the Union Government have received any request for the construction of by-pass on National Highway No.7 in Rewa district of Madhya Pradesh;

(b) if so, the details in this regard;

(c) the present status of the proposal; and

(d) the reasons, if any for the delay in this regard?

Answer given by the minister

THE MINISTER OF STATE OF THE MINISTRY OF ROAD TRANSPORT AND HIGHWAYS (MAJOR GENERAL (RETD.) B.C. KHANDURI)

(a) to (d) Yes, Sir. Construction of Rewa Bypass on NH-7 in Madhya Pradesh is to be on Build Operate and Transfer (BOT) system. Its likely cost is Rs. 40.55 crore. An amount of Rs. 3.63 crore was sanctioned in 2000 for land acquisition for this bypass. Necessary land acquisition has been completed in March, 2002 and shifting of utilities such as shifting of High Tension (HT)/Low Tension (LT) lines by the State Government is pending. The delay has been due to the modification in the alignment.