(a) the present status of Subarnarekha Inter-State project;
(b) the target date when the project is likely to be
completed; and
(c) the funds allocated and actual amount spent on the
project so far?
(a) the present status of Subarnarekha Inter-State project;
(b) the target date when the project is likely to be
completed; and
(c) the funds allocated and actual amount spent on the
project so far?
THE MINISTER OF STATE IN THE MINISTRY OF WATER RESOURCES (SMT. BIJOYA CHAKRAVARTY)
(a) to (c) The present status of Subarnarekha Inter-State
Project is as under:-
(Rs. in crore)
Sl Name of the project Approved Tenth Outlay Expendit No. cost Plan for ure upto (Year) Outlay 2002-03 3/2002
1. Subarnarekha 1428.82 205.73 53.00 855.59 Multipurpose (1990) Project, Jharkhand
2. Subarnarekha 1013.68 100.30 30.00 452.84 Irrigation Project, (1993) Orissa
3. Subarnarekha Barrage 595.34 375.00 6.00 33.92 Project West Bengal (1996)