THE MINISTER OF STATE IN THE MINISTRY OF URBAN DEVELOPMENT (SHRI BABUL SUPRIYO)
(a) & (b) AS per the information provided by the Metro Rail Companies, the details of the sections of the metro rail projects awaiting safety clearance from Commissioner of Metro Rail Safety (CMRS), are as below:
Sl. Name of the Metro Section of the Metro Project Remarks No. Rail Project awaiting safety clearance
1. Jaipur Metro Rail Projects Phase-1A (Mansarovar to Chandpur; CMRS has started the inspection 9.718 km ) procedure in March 2015
2. Chennai Metro Rail Projects Koyambedu to Alandur; 10.00 km(app.) CMRS has started the inspection process on 06.04.2015
Safety of passengers travelling in metro rail is paramount. The safety certification of metro rail projects is exhaustive and involves many tests and tiers/organizations each having their own internal processes.Safety clearance of Metro Rail Projects is granted by the CMRS after detailed examination and due diligence.
(c)&(d):Safety certification of Metro Rail Projects is done by the CMRS which is an independent agency under the administrative control of Ministry of Civil Aviation.
(e): Chennai Metro Rail Ltd. has informed that there has been no loss and Jaipur Metro Rail has informed they have not assessed the loss.