Question : NHDP PHASE 3-A AND 3-B



(a) Whether there is any proposal for strengthening of the National Highways and converting 890 km. of N.Hs. into four and six lanes under B.O.T. based N.H. Development Project phase 3A and 3B in Bihar;

(b) if so, the details thereof;

(c) whether the Union Government provides 40 of grants for the project and the rest of the amount is mobilized from the entrepreneurs;

(d) if so, whether the work on the said project has not been started;

(e) if so, the reasons therefor;

(f) whether the Government proposes to implement these projects in Bihar through Central Agencies providing full grants for the purpose; and

(g) if so, the time by which the same is likely to be implemented and if not, the reasons therefor?

Answer given by the minister

THE MINISTER OF STATE IN THE MINISTRY OF SHIPPING, ROAD TRANSPORT AND HIGHWAYS (SHRI K.H. MUNIYAPPA)

(a) and (b) 9 stretches of various National Highways as per details given below having a total length of 890 km have been identified for four laning under National Highways Development Project (NHDP) Phase III in Bihar. None of these stretches has been approved under NHDP Phase-III A for implementation on BOT basis.

Sl. No.	Route	NH No.	Length (km.)
1. Purnea-Khagaria-Begusarai-Barh-Bakhtiarpur 31 255
2. Bakhtiarpur-Patna 30 53

3. Patna-Hazipur-Muzaffarpur(excluding Muzaffarpur 19, 77 46.3 bypass) Muzaffarpur bypass 77 13.7

4. Motihari-Raxaul 28A 67

5. Forbesganj-Jogwani 57A 13 6. Gopalganj-Chapra-Hajipur 85, 19 153

7 Buxar - Patna 84, 30 130

8. Muzaffarpur - Sonbersa 77 89

9. Mokama-Munger 80 70
TOTAL 890



(c) Yes, Sir.

(d) Detailed Project Report for these projects is under preparation. Implementation of projects will be taken up after process of selection of entrepreneurs is completed.

(e) Bids for two works, viz., Patna-Bakhtiarpur section of NH-30 and Hajipur-Muzaffarpur section of NH-77, were invited on `Build-Operate-Transfer` (BOT) basis and there was no response from the entrepreneurs. Besides, Detailed Project Report (DPR) has been completed for an aggregate length of 80 kms only of NH-57A and 28A. Preparation of DPR for the remaining stretches is in progress.

(f) No, Sir.

(g) Does not arise.