Question : GAUGE CONVERSION OF ARASIKERE-HASSAN-MANGALORE RAILWAY LINE



(a) the date on which the gauge conversion work of Arasikere-Hassan-Mangalore Railway line was started;

(b) the estimated cost of the above project and the amount spent thereon so far;

(c) the funds allocated to the above project during 1999-2000; and

(d) the time by which the above project is likely to be completed?

Answer given by the minister

MINISTER OF STATE IN THE MINISTRY OF RAILWAYS (SHRI DIGVIJAY SINGH)

(a): The work was started in the year 1994-95.

(b): The cost of the project is Rs. 217.82 crs. and an amount of Rs. 115.01 crs. has been spent so far.

(c): The budget allotment in 1999-2000 was Rs. 28 crs.

(d): Arsikere-Hassan (46.66 km) was commissioned on 23.8.96 and Hassan to Sakleshpur (42.06 km) was commissioned on 26.01.98. The work on Sakleshpur-Kankanadi (142 km) is in good progress and will be completed in a phased manner. No firm target date has yet been fixed for the completion of the project.