THE MINISTER OF STATE IN THE MINISTRY OF ROAD TRANSPORT AND HIGHWAYS
(SHRI JITIN PRASADA)
(a) The State of Gujarat is served by 13 number of National Highways namely
National Highway no. 6,8,8A,8B,8C,8D,8E,14,15,59,76A,113 & 228 having aggregate
length of 3188 km and one National Expressway (NE-1) from Ahmedabad to Vadodara
having length of 93.0 km.
(b) The National Highways converted into four lanes are at Annex.
(c) The part of Golden Quadrilateral passing through the State of Gujarat is
National Highway no. 8 from Rajasthan/Gujarat border to Ahmedabad, National
Expressway from Ahmedabad to Vadodara and National Highway no.8 from Vadodara
to Gujarat/Maharashtra border.
(d) Yes, Madam. There has been delay in completion of two on-going road
works namely four laning of Gagodhar to Garamore of NH-8A and six-laning of
Surat-Dahisar section of NH-8. These works also include construction of
structures such as bridges, flyovers and ROBâs, etc. falling on the stretches
as per required lane width. In addition, three bridge works at km. 68/200, km.
78/200, km. 190/00 of NH-8A are running behind schedule.
(e) Land acquisition, change in scope, unfavourable climatic condition,
technical problem and delay on the part of concessionaire are the reasons for
delay in completion of works. The likely time frame for completion of said
works is March, 2012.