THE MINISTER OF STATE FOR JAL SHAKTI
(SHRI PRAHLAD SINGH PATEL)
(a) & (b) Since August, 2019, Government of India in partnership with States is implementing Jal Jeevan Mission (JJM) to make provision of potable tap water supply to every rural household across the country, by 2024.
At the time of announcement of Jal Jeevan Mission, 3.23 Crore rural households were reported to have tap water connections. So far, 6.65 Crore households have been provided with tap water connections in last 35 months. Thus, as on 25th July 2022, out of 19.14 Crore rural households in the country, around 9.88 Crore (51.61%) households are reported to have tap water supply in their homes.
(c) Drinking Water being a State subject. It is States, who plan, design, approve and implement drinking water supply schemes. Government of India supplements the efforts of the States by providing technical and financial assistance. As such details of district wise fund allocation is not made and maintained by this department. However, details of Central fund allocated, fund drawn and fund utilization reported by the State of Rajasthan under Jal Jeevan Mission in 2019-20, 2020-21, 2021-22 and 2022-23 (as on 25.07.2022) is as under:
(Amount in Rs. Crore)
Year Central share Expenditure under State share
Opening Balance Allocation Fund drawn by the State Total fund available Reported utilization
2019-20 313.67 1,301.71 1,301.71 1,615.38 620.31 698.54
2020-21 995.07 2,522.03 630.51 1,625.58 762.04 789.05
2021-22 863.53 10,180.50 2,345.08 3,208.61 1,763.79 1,497.57
2022-23 1,288.46 13,328.60 ND 1,288.46 461.34 489.69
Source: JJM, IMIS ND: Not Drawn
(d) to (f) As informed by the State, for supply of drinking water, the villages of parliamentary constituencies of Sikar being covered from Indira Gandhi Nahar Pariyojana & Phase II of Isarda Dam. Similarly, Alwar is being covered from by bulk water taken from Chambal river & Phase II of Isarda Dam. The Dholpur-Karauli and Bharatpur are being covered through bulk water taken from Chambal River. Details of status of detailed project report (DPR) in the villages under these constituencies are as under:
S. No. Parliamentary Constituency Total Villages (2011 Census) Villages where DPR is approved Villages where DPR is under preparation Villages where DPR preparation yet to start
(1) (2) (3) (4) (5) (6) = (3)-(4)-(5)
1. Bharatpur 1,627 977 650 0
2. Dholpur-Karauli 1,654 468 383 803
3. Sikar 1,130 170 960 0
4. Alwar 1,385 0 1,385 0
*****