Question : PENDING HYDRO POWER PROJECTS



(a) the number of power projects still pending with the National Hydro Power Corporation (NHPC);

(b) whether the Government of Uttaranchal has transferred three Hydro Electric Projects to NHPC recently;

(c) if so, the details thereof; and

(d) the time by which these projects are likely to be operative?

Answer given by the minister

THE MINISTER OF POWER (SHRI SUSHILKUMAR SHINDE)


(a) : The work on none of the sanctioned projects of National Hydroelectric Power Corporation Limited (NHPC) is pending except in the case of the Loktak Down Stream Hydroelectric Project (90 MW) in Manipur. The work on the Loktak Down Stream Hydroelectric Project could not be started due to adverse law and order situation prevailing in the State and lack of proper approach road to the project site.


(b) to (d) : The details of the projects located in the State of Uttaranchal, which have been entrusted/transferred to NHPC for survey, investigation and execution are given below:

Sl.	Name of the	Installed	Likely Construction period from the date
No.	Project	Capacity (MW)	of investment approval (After completion	of survey and investigation, preparation of	Detailed Project Report (DPR) and	obtaining all clearances)
1 Lakhwar Vyasi 420 4 yrs 6 months 2 Kotli Bhel-1A 195 4 yrs 6 months 3 Kotli Bhel-1B 320 4 yrs 6 months 4 Kotli Bhel-II 530 4 yrs 9 months 5 Chungar Chal 240 5 yrs 9 months 6 Garba Tawaghat 630 5 yrs 9 months 7 Kharmoli Lumti Tulli 55 4 yrs 6 months