MINISTER OF STATE IN THE MINISTRY OF PARLIAMENTARY AFFAIRS
AND MINISTER OF STATE IN THE MINISTRY OF RAILWAYS ( SHRI O. RAJAGOPAL )
(a) : No demand has been received from Government of Orissa
in the current year for additional allocation of funds for
the railway projects in Orissa.
(b) : Does not arise.
(c) & (d) : Details of projects in Orissa including their
cost, anticipated expenditure upto March, 2002, and
outlay for 2002-03, along with the status of each
work is given at Appendix. Target dates of completion
whenever fixed are included in the status of the
projects.
APPENDIX
APPENDIX REFERRED TO IN REPLY TO PARTS (c) & (d) OF LOK SABHA UNSTARRED
QUESTION 6619 FOR 9.05.2002
On-going Railway Projects in Orissa
S. Name of Rly. Latest Outlay Budget Status
No. Project Antici expect Outlay
p-ated ed to for
Cost end of 2002-
2001- 03
02
(Amount in Crores of Rupees)
Doubling
1 Jharsuguda bye- SER 19.62 0.00 0.50 New work included in
pass Budget 2002-03 and is
being taken up.
2 Khurda Road- SER 47.29 6.80 5.00 Contract for earthwork
Puri Phase-I and minor bridges for
(Khurda Road- section I covering 6.5
Delang) km. from Khurda Road
and major bridge no.17
awarded and work is in
progress.
3 Nergundi- SER 112.86 61.72 10.00 Detailed estimate for
Cuttack- this work has been
Raghunathpur sanctioned. Earthwork
& bridges are in
progress on Nergundi-
Kendrapara Road
section and
Raghunathpur-Cuttack
section. Nergundi-
Kendrapara is planned
for completion during
2002-03.
4 Raghunathpur- SER 67.99 65.19 0.68 Completed and
Rahama commissioned.
5 Rahama- SER 40.95 24.06 10.00 Detailed estimate has
Paradeep been sanctioned. Land
acquisition in 27
villages has been
takenover. Earthwork
& minor bridges are
in progress.
6 Rajatgarh- SER 166.16 0.05 5.00 Requisite clearances
Barang have been obtained.
Final location survey
completed from
Radhakishorepur to
Barang.
7 Rajatgarh- SER 82.86 75.66 3.50 The section from
Nargundi Rajatgarh to Salegaon
has been completed.
The balance section
from Salegaon to
Nergundi (6 km ) is
targeted for
completion during 2002-
03.
8 Sambalpur- SER 48.50 0.00 0.50 New work included in
Rengali Budget 2002-03 and is
being taken up.
9 Talcher- SER 104.26 5.33 20.00 2nd Bridge on Birupa
Cuttack- River :- Soil
Paradeep (2nd investigation and
Bridges on detailed design has
Mahanadi & been completed.The
Birupa ) tender for bridge
has been processed.
2nd bridge on
Mahanadi River:
Consultant has
submitted the design
and drawings. Tenders
for bridge will be
invited once design is
finalised.
10 Titlagarh- SER 100.05 46.90 15.00 Earthwork and Bridges
Lanjigarh are in progress.
Kesinga - Norla Road
(23 km ) is targeted
for completion during
2002-03.
Gauge Conversion
11 Naupada- SER 66.35 0.04 10.00 Work will be taken up
Gunupur after obtaining the
requisite clearances.
12 Rupsa- SER 78.94 11.90 5.00 In Ph- I, gauge
Bangariposi conversion of Rupsa-
Baripada section (52
km ) is planned.
Earthwork and bridges
are in progress.
New Lines
13 Angul-Sukinda SER 245.58 0.68 1.00 Final Location Survey
Road has been completed.
Soil exploration for
all 17 major bridges
has been completed.
14 Daitari- SER 537.74 345.77 40.00 The Line from
Banspani Banspani to Joruli (11
km) has been
completed. In the
remaining portion,
earthwork, bridgework
and other works are in
progress. Section
from Joruli to
Keonjhar is targeted
for completion during
2002-03.
15 Haridaspur- SER 301.64 16.17 5.00 Final location survey
Paradeep has been completed.
Land acquisition plans
and papers have been
submitted to State
Govt. Work would be
progressed as per
availability of
resources.
16 Khurda Road- SER 700.00 14.16 5.00 The work of final
Bolangir location survey is in
progress . Land
acquisition papers for
26 villages from
Khurda end submitted
to State Govt. The
work in first 2.5 km
of length from Khurda
Road end has commenced
where land has been
handed over by State
Govt. Rs.3.66 cr has
so far been deposited
with the State Govt.
for land acquisition.
17 Koraput- SER 479.45 479.44 0.01 The work has been
Rayagada completed and
commissioned.
18 Lanjigarh Road- SER 100.05 16.93 2.00 In phase-I, work has
Junagarh been taken up from
Lanjigarh to
Bhawanipatna (31 Km).
Eathwork and bridge
works are in progress.
19 Talcher- SER 478.51 455.01 0.01 Completed and
Sambalpur commissioned.
Railway Electrification
20 Bhubaneshwar- SER 319.64 275.45 30.00 The entire section
Kottavalasa energised and electric
traction introduced.
Electrification of
Khurda Road-Puri
section (44 RKM) as an
extension of this
project has been taken
up which is likely to
be completed by March,
03.
21 Bokarao Steel SER 269.81 265.24 4.57 Entire section
City-Muri- energised till March,
Hatia- 2002. Residual works
Bondamunda- are in hand. The
Bimlagarh- project has been
Kiriburu/Barsu delayed due to bad law
an incl. and order problem and
Purulia- failure of OHE
Kotshila contractor and delay
in release of 132 KV
supply by DVC/BSEB.
22 Kharagpur- SER 317.36 192.45 21.57 110 RKM energised
Bhubaneswar till March, 2002. The
including work is in progress
Talcher- and targeted for
Paradeep completion by March,
2003.