THE MINISTER OF STATE IN THE MINISTRY OF SHIPPING,
ROAD TRANSPORT AND HIGHWAYS (SHRI K. H. MUNIYAPPA)
(a) National Highways Authority of India (NHAI) has identified 17 contracting firms (nine Indian and eight foreign)
as non-performing contractors on the basis of review of their performance for implementation of projects awarded
to them.
(b) The names of non-performing contractors alongwith the projects delayed by each of them are given at
Annexure-I.
(c) The non-performing contractors are liable for penalty in form of liquidated damages for delay stipulated in the
civil work contract (at specified percentage @ 0.05% of contract value per day subject to maximum 10% of the
contract value).This penalty is for the delay because of reasons attributable to the contractors which also include
non-performing contractors.
NHAI has criteria for judging the non-performing contractor(s) and as a policy non-performing contractors do not
pre-qualify for award of any future contract in NHAI till their performance improves in course of subsequent review.
ANNEXURE-I
ANNEXURE REFERRED TO IN REPLY TO PART (b) OF LOK SABHA UNSTARRED QUESTION
NO. 2270 FOR ANSWER ON 29TH AUGUST, 2007 ASKED BY SHRI P.S. GADHAVI REGARDING
BLACK-LISTING OF COMPANIES/CONTRACTORS.
LIST OF NON-PERFORMING CONTRACTORS AND THE DETAILS OF PROJECTS DELAYED INDIAN
FIRMS
S. No. Name of the Firm Projects Delayed
1. Ashwani Construction Company, Etawah Bypass New Delhi.
2. Afcons Infrastructure Ltd., Hubli â Haveri Mumbai. Kanchipuram â Poonamalee Nandi Hills Cross to Devanhalli & Six laning of Meenukunte to Habbal (NS-24/KN)
3. A.L. Sudershan Cons. Co. Ltd., Tumkur Bypass Hyderabad. Kalkallu village to Gundla Pochampali (NS-8) Chitradurgha Bypass
4. APIL (Subsidiary of Afcons Hubliâ Haveri Infrastructure Ltd.),AFCONS-APIL (JV), Mumbai.
5. Bhageeratha Engineering Ltd, Bridges section (WB-III) New Delhi. Thumpipadi to Salem (NS-26/TN) 4. laning of Karur Bypass including additional bridge across river Amarawati Garhmukteshwar âMuradabad Etawah Bypass
6. DD Builders Ltd., Bhubaneshwar- Ganjam - Icchapuram (Orissa).
7. M/s Essar Group, Mumbai. Haveri â Harihar (Terminated) HariharâChitradurga (Terminated) Chitradurga - Sira
8. Lanco Construction, New Delhi. Dalkola Islampur Sub section 2(EW/6) Purnea - Gayakota (EW-12/BR)
9. Rani Construction, New Delhi. Purnea - Gayakota (EW-12/BR)
FOREIGN FIRMS
S. No. Name of the Firm Projects Delayed
1. Bhumihighway, Venture Berhad (400463-M), Bhogpur to Jalandhar (NS-16/PB) Selangor-Darul Ehsan, Malaysia. Ganjam â Icchapuram
2. Centrodostroy, Moscow, Russia. Fatehpur - Khaga (TNHP/II-C) Handia - Varanasi (TNHP/III-C)
3. China Coal Construction Group Shikohabad â Etawah Corporation, Beijing, China.
4. Dolomite Inudstries Co. Sdb. Bhd, Chitradurga bypass Selangor Darul Ehsanm,Malaysia.
5. PATI-SDN-BHD, Kuala Lumpur, Etawah - Rajpur (GTRIP/I-C) Malaysia. Dhankuni - Kolaghat (WB-I)
6. Sticco, Kingdom of Saudi Sunakhala - Ganjam (OR-VII) Arabia.
7. UEM Builders (6551-K), Kuala- Haveri â Harihar (Terminated) Lumpur, Malaysia. HariharâChitradurga (Terminated) Chitradurga - Sira
8. You-one Engineering Construction Srikakulam to Champawati Co. Ltd,Seoul Korea. Eight Laning of Haryana/ Delhi Border to Mukarba Chowk Gundla Ponchampalli to Bowenpalli