(a) whether the Government has sanctioned sufficient amount during the current financial year to complete Dhar-Makshi-Godhara Railway Line;
(b) if so, the details thereof; and
(c) if not, the reasons therefor?
(a) whether the Government has sanctioned sufficient amount during the current financial year to complete Dhar-Makshi-Godhara Railway Line;
(b) if so, the details thereof; and
(c) if not, the reasons therefor?
MINISTER OF STATE IN THE MINISTRY OF RAILWAYS ( SHRI R. VELU )
(a): No, Sir. An outlay of Rs. 15 crore could only be provided for the project during 2004-05.
(b): Does not arise.
(c): Constraint of resources.