THE MINISTER OF STATE IN THE MINISTRY OF POWER (SHRI K.C. VENUGOPAL)
(a) : As on 25th August, 2012, 22 power projects of NTPC and its
Joint Venture Companies having total capacity of 16,809 MW are under
construction. State-wise details are placed at Annex-I.
(b) & (c) : A few projects of NTPC are delayed for various reasons. The
State-wise original schedule of the projects along with reasons for delay
are given at Annex-II.
(d) : The following corrective measures have been taken by NTPC:
1. NTPC is making a data base for pre-qualified contractors in civil
and other infrastructure areas in order to have wider vendor
base. Enlistment of civil agencies for main plant civil packages,
site leveling and infrastructure development, start up ash dyke
and ash dyke raising done.
2. The progress of BHEL supplied projects is being reviewed at
various levels in NTPC, BHEL, Central Electricity Authority &
Ministry of Power.
3. NTPC is making efforts to expedite supply of materials
including diversion of equipment from one project to another
whenever required to ensure installation and timely
commissioning of projects.
4. NTPC has developed IT based Project Monitoring Systems for
ongoing projects for monitoring the progress on daily basis.
5. To reduce execution time of project, NTPC is also considering
EPC (engineering, procurement & construction) concept and
reduction of number of packages for other projects.
6. Simplification of lay out for reduction in interface with vendors.
7. NTPC has created special cells for land acquisition and forest
clearance consisting of experts from NTPC as well as outside.
8. Placement of team s at vendor workshop for expediting
deliveryofcritical items.
9. Monitoring of Over Dimension Consignment (ODC) items through
Global Positioning System (GPS).
10. Action has been taken for solving contractual issues such (a)
as General Conditions of Contract (GCC) for civil works have
been revised, (b) price variation ceiling for hydro projects has
been revised, (c) procedure for hiring of Tools and Plants (T&P)
by projects has been issued.
(e) & (f) : Government of India do not set up Power Projects. However,
Central Public Sector Undertakings (CPSUs) of Government set up power
projects in various parts of the country. Besides power projects are also
set up in State & Private Sector. List of Projects for likely benefits during
12thPlan as per the report of Working Group on Power for 12th Plan is at
Annex-III.