(a) the total cost of the Hasdeo Bango Project in Bilaspur division in Chhattisgarh and the expected benefits accrued therefrom;
(b) the extent to which the benefits have been accrued; and
(c) the time by which the project is likely to be
completed?
(a) the total cost of the Hasdeo Bango Project in Bilaspur division in Chhattisgarh and the expected benefits accrued therefrom;
(b) the extent to which the benefits have been accrued; and
(c) the time by which the project is likely to be
completed?
THE MINISTER OF STATE IN THE MINISTRY OF WATER RESOURCES (SMT. BIJOYA CHAKRAVARTY)
(a) The latest estimated cost of the Hasdeo Bango
Project is Rs. 1043.54 crores including the completion cost
of Phase I & II (Rs. 23.54 crores). The estimated benefits
are 434 th. ha. irrigation and 120 mw hydro power (3X40 mw).
(b) 157.5 th. ha. potential has been created till
March, 2000. All the 3 hydro power units have also been
commissioned.
(c) Completion of the project is linked to provision
of necessary funds by the State Government. The Central
Government is assisting the project with assistance under
Accelerated Irrigation Benefits Programme and so far, Rs.
30.780 crores has been released under this assistance.