Question : WIDENING OF MODINAGAR HARIDWAR NATIONAL HIGHWAY



(a) whether the Government proposes to carry out widening and metalling of the NH from Modinagar to Haridwar and to put up dividers thereon in view of the heavy traffic;

(b) if so, the time by which the said work is likely to be started; and

(c) if not, the reasons therefor?

Answer given by the minister

THE MINISTER OF STATE IN THEMINISTRY OF SHIPPING, ROAD TRANSPORT AND HIGHWAYS (SHRI K.H. MUNIYAPPA)

(a) to (c) The Modinagar-Haridwar section of National Highway is part of Delhi-Haridwar section of NH-58 which is identified for 4-laning/6-laning with the provision of dividers under NHDP Phase-IIIA. The status is as under:-

i) Delhi/UP Border-Meerut (46 km) is already 4-laned. Work for preparation of DPR for 6 laning is in progress.


ii) Meerut-Muzaffarnagar Section (79 km): The work of 4-laning on BOT basis has been awarded.


iii) Muzaffarnagar-Haridwar section: BOT bids had been invited in May, 2006. The single BOT bid was received, which has been cancelled. Process for re-bidding has been initiated.