THE MINISTER OF STATE IN THE MINISTRY OF SHIPPING, ROAD TRANSPORT AND HIGHWAYS
( SHRI K. H. MUNIYAPPA )
(a) Under North-South Corridor project, a length of 3699 km has been envisaged for upgradation
to 4/6/8 lane. Out of this, 4/6/8 â laning of 1385 km have been completed. A length of 1724 km
are under implementation and the balance 590 km are yet to be awarded.
(b) and (c) Partly, the work on Sengapalli to Cochin stretch i.e. Sengapalli to Walayar section
in Tamilnadu and Walayar to Thrissur section in Kerala has been delayed due to delay in preparation
of feasibility report and detailed project report by the Consultant.
(d) Regular monitoring is being done at various levels to expedite pre-construction activities
such as land acquisition, utility shifting, environmental clearances, etc. so as to achieve smooth
progress during construction.
(e) The work on Sengapalli to Walayar section in Tamilnadu and Walayar to Thrissur Section in
Kerala is yet to be awarded. Work on Thrissur to Angamalli is targeted for completion by March,
2009 and 4-laning of Angamalli to Cochin is already completed.