MINISTER OF THE STATE IN THE MINISTRY OF PARLIAMENTARY AFFAIRS AND WATER RESOXJRCES (SHRI PAWAN KUMAR BANSAL)
(a)to(e) A Statement is laid on the Table of the House.
Statement referred to in reply to part (a) to (e) of Lok Sabha Starred question No.381 regarding
`Irrigation Projects` due for reply on 16.12.2009
(a) & (b): Details of major and medium irrigation projects under Accelerated Irrigation Benefits Programme
(AIBP) presently being implemented are given in Annex-I and details in respect of surface Minor Irrigation
(MI) schemes under AIBP are given in Annex-H. Ultimate irrigation potential planned to be achieved on
completion of all the projects/ schemes is 123.56 lakh ha.
(c) Funds allocated under AIBP during 2006-07 to 2008-09 were Rs. 2098 crore, Rs. 3080 crore and Rs. 6600
crore respectively. The fund allocated during 2009-10 is Rs. 8000 crore. The releases made under the AIBP
during 2006-07 to 2009-10 till date are Rs. 2301. 9722 crore, Rs. 5445. 7051 crore, Rs. 7598. 2213 crore
and Rs. 3147. 3909 crore respectively. State wise break up of releases is given in Annex-III.
(d) A copy of the updated guidelines for the AIBP is given in Annex-IV.
(e) In order to expedite completion of the projects, the Ministry of Water Resources and Central Water
Commission have established an extensive monitoring mechanism through Monitoring field offices, which
monitor the projects under their respective jurisdiction in the light of guidelines established for
the purpose. High level meetings with the senior officers of state governments are held for monitoring
the progress and providing guidance to the project authorities for speedy completion of the projects,
A Memorandum of Understanding (MOU) is signed with the state government in respect of each major/medium
irrigation project and each MI project comprising a group of individual schemes containing year-wise
physical targets of potential creation till its completion. The guidelines provide that central assistance
under AIBP is released only on achievement of physical target by the state government in the previous year.
The MOU also provides for target date of completion of the project. However, in cases where delay in
execution of projects is beyond the control of the state government, extension of time is required to
be sanctioned after the state government provides full justification for delay in completion of the
project.