THE MINISTER OF POWER
(SHRI P.R. KUMARAMANGALAM)
(a) to (f) : A Statement is laid on the Table of House.
STATEMENT
STATEMENT REFERRED TO IN REPLY TO PARTS (a) TO (f) OF STARRED
QUESTION NO.55 TO BE ANSWERED IN THE LOK SABHA ON 28.2.2000
REGARDING FUNDS TO SEBs TO UNDERTAKE TRANSMISSION AND
DISTRIBUTION.
(a) : The Government is considering to introduce a new
scheme under which funds will be provided to power utilities to
undertake investment in sub-transmission and distribution
projects including the provision of meters at all levels with the
object of reducing T&D losses and improving the operational
efficiency of State Power Utilities. However, release of funds
would be contingent on the State Government accepting
conditionalities with regard to reform and restructuring.
(b) : The financial position of State Electricity Boards
for the year 1997-98 is given in the enclosed Statement
(Annexure-I).
(c) & (d) : Government of Orissa has submitted a proposal for
financial restructuring of Grid Corporation of Orissa (GRIDCO)
which includes, inter-alia,
Conversion of GRIDCO`s payables to the generators totalling
Rs.1160.4 crores as on 31.3.2000, into tax free bonds;
Re-schedulement of loans to PFC and REC and
Soft loan of Rs.206 crores from the World Bank (in addition
to the US $ 350 million loan already sanctioned by World
Bank).
The Government of Andhra Pradesh has requested for
Government of India`s recommendation for availing special
assistance of Rs.1000 crores (50% as grant and 50% as loan)
from the World Bank, in order to support the State
Government`s restructuring efforts in the power sector.
The Government has signed a Memorandum of Agreement with the
Government of Karnataka on 12.2.2000. The Agreement
provides for, among other things, Government of India`s
commitment for financial support to the State.
To upgrade its sub-transmission and distribution network in
a phased manner;
For executing the system loss reduction programme.
For adequate funding through REC for 100% electrification of
villages and hamlets and
For undertaking studies on reforms and restructuring through
PFC grant and interest free loans.
For assisting the State Government in raising funds from
financial institutions and other sources.
(e) & (f) : Details of loans provided by foreign financial
institutions to SEBs for Transmission and Distribution works
during the last 3 years are given at Annexure-II.
Annexure-I
Annexure referred to in reply to Part (b) of Lok Sabha Starred Question No.55 to be answered on 28.2.2000 regarding details of commercial loss/profit (with and without subsidy) of SEBs.
Statement indicating the profit and loss incurred by State Electricity Boards asper 1997-98 accounts. (Without subsidy)
Name of the SEB (Rs. Crores) 1. APSEB -1134.46 2. ASEB - 439.58 3. BSEB - 225.42 4. GEB -1363.62 5. HSEB - 712.79 6. HPSEB - 29.45 7. KEB - 321.77 8. KSEB - 296.70 9. MPEB - 753.01 10. MSEB 36.61 11. MeSEB - 52.00 12. OSEB 13. PSEB - 555.27 14. RSEB - 639.53 15. TNEB - 317.75 16. UPSEB -1547.97 17. WBSEB - 164.18 ALL SEBs -8457.99 OSEB was restructured w.e.f 1.4.1996.
Annexure-II
Annexure referred to in reply to Lok Sabha Question No.55 Part (e&f) to be answered on 28.2.2000 regarding details of External Assistance to S.E.B`s for undertaking T&D Projects During Last 3 Years.
Sl.No. Name of Project State Funding 1999- 1998- 1997- TOTAL Agency 2000 1999 1998 1. Orissa Power Sector Restr. Orissa IBRD 50.00 70.00 87.50 207.50 2. Haryanan Power Sector Restr. Haryana IBRD 93.00 70.00 0.00 163.00 3. A.P. Power Power Sector Restr. A.P. IBRD 60.00 33.86 0.00 93.86 4. Automation in Chennai Metro T.N. ADB 33.00 22.64 67.40 123.04 5. Power System Improvement Multi/RE JBIC 100.00 75.00 63.02 238.02 6. Srisailam Power Trans. A.P. JBIC 188.80 115.00 222.15 525.95 7. Anpara Power Trans. U.P. JBIC 100.00 105.00 236.23 441.23 8. W.B. Trans. System W.B. JBIC 70.00 4.00 0.00 74.00 9. Simhadri and Vizag Trans. A.P. JBIC 20.00 18.00 0.00 38.00 10. A.P. Energy Efficiency Proj. A.P. U.K. 15.00 8.00 30.30 53.30 11. Orissa Power Sector Restr. Orissa U.K. 19.00 62.15 63.12 144.27 12. Power Efficiency Improvement/lulti/PF( IBRD 0.00 72.12 350.00 422.12 13. Power Efficiency Improvement/lulti/PF( ADB 0.00 176.03 385.13 561.16 TOTAL 748.80 831.80 1504.85 3085.45
Covered in ADB Loan for Second North Madras Power Project.