THE MINISTER OF STATE IN THE MINISTRY OF ROAD TRANSPORT AND HIGHWAYS(SHRI R.P.N.SINGH)
(a) There are 15 National Highways in Gujarat namely NH-6, NH-6(Ext.), NH8, NH-8A,
NH-8A(Ext.), NH-8B, NH-8C, NH-8D, NH-8E, NH-8E (Ext.), NH-14, NH-15, NH-59, NH-113 and NH-228.
Apart from this, there is one National Expressway NE-1 in Gujarat. The total length of National
Highways in Gujarat is about 3233 kms. Out of the total length, about 1576 km are four lane or
more.
(b) On-going projects undertaken by NHAI in Gujarat are Annexed.
(c)&(d) The widening of National Highways to four lanes is taken up depending upon the inter se
priority , traffic needs and availability of funds . However, 1700 km of NH in the state of
Gujarat has been identified/undertaken for 4-laning by NHAI under NHDP Phase I, II and III.
The section between Godhara and Dahod, fall on NH â59 which connects to Indore.However,
DahodâHalol falls on State Highway. The entire section of NH-59 in Gujarat i.e.
Ahmedabad-GodharaâGujarat MP Border (Km 4.20 to Km 215.900) has been identified for four laning
under NHDP Phase III on BOT (Toll) basis. Request for Qualification (RFQ) for pre-qualification
of bidders for the section has been invited.
Â
The project is targeted for award during the year 2009-2010.After award, it may take about 3 years
to complete the project.
ANNEXURE
ANNEXURE REFERRED TO IN REPLY TO THE PART (b) OF LOKSABHA UNSTARRED QUESTION NUMBER 366 TO BE
ANSWERED ON 07.07.2009 ASKED BY SHRI P.P.CHAUHAN REGARDING NATIONAL HIGHWAYS IN GUJARAT
Â
List of Projects currently under implementation by NHAI in the state of Gujarat Â
Â
Stretch NH No. Total Length
NHDP Phase II
Garamore to Bamanbore(Package-III) 8A 71.4
Gagodhar to Garamore(Package-IV) 15,8A 90.3
NHDP Phase III
Gujarat/Maharashtra Border-SuratâHazira Port section 6 132.9
NHDP Phase V
Vadodara to Bharuch Package BOT-I(Six lane) 8 83.3
Bharuch to Surat Package BOT-II(Six lane) 8 65
SuratâDahisar(six lane) 8 239