(a) & (b) The details of abandoned/discontinued projects
of CIL during the last three years and the current year are
given below:
S. Subsidiary State Name of Mine Reason
No.
1 Eastern West Sangramgarh On economic & safety Coalfields Bengal Underground ground Limited (UG)
2 Eastern West Madhusudanpur On exhaustion of Coalfields Bengal 3&4 Pit accessible reserve in Limited the unit.
3 Western Madhya Pench East Exhaustion of mineable Coalfields Pradesh Opencast (OC) reserve. Limited (WCL)
4 Western Maharashtra Inder UG Uneconomic Coalfields Limited
5 Western Madhya Pathakhera-1 Exhaustion of reserve. Coalfields Pradesh Limited
6 South Eastern Madhya Nowrozabad Exhaustion of reserve. Coalfields Pradesh (East) UG Limited
7 South Eastern Madhya Kotma West Exhaustion of reserve Coalfields Pradesh UG Limited
8 South Eastern Chhattisgarh Jainagar 5&6 Extractable reserve Coalfields exhausted Limited
9 South Eastern Chhattisgarh Kumda Old UG Exhaustion of reserve Coalfields Limited
10 North East Assam Tipong UG Production suspended Coalfields due to imposition of Sec. 22 (3) of Mines Act on 07.11.2008.
11 North East Assam Ledo UG The mine was sealed Coalfields off from surface on 07.11.2008 due to dangerous occurrence on 04.11.2008 & 07.11.2008.
12 North East Assam Baragolai UG Production suspended Coalfields due to imposition of Sec. 22 (3) of Mines Act on 07.11.2008.
(c): No Sir, the workforce has been redeployed in other
working mines.
(d): In view of the reply to part (c) above, question does not
arise.