MINISTER OF THE STATE IN THE MINISTRY OF ROAD TRANSPORT AND HIGHWAYS (SHRI JITIN PRASADA)
(a) &(b) Four âlaning of Jetpur-Somnath Section of NH-8D has been approved and awarded by NHAI and Financial Close has been achieved by
the Concessionaire. However, the appointed date could not be notified pending public hearing of 14 villages in Junagadh bypass section
owing to judgment of Honâble High Court of Gujarat. The Feasibility Study for widening and improvement of Bhavnagar-Pipavav-Porbandar
-Dwarka section of NH-8E in the state of Gujarat has been carried out by NHAI through Consultant. However, the approval for the project
implementation of NH-8E has not been accorded.
(c) These projects are taken up/envisaged under Public-Private Partnership mode.
(d) The fourlaning work on NH-8D shall commence after notification of appointed date. The completion period as per the concession agreement
is 30 months.