Question : GAUGE CONVERSION



(a) whether the Railways had sanctioned for Chinna Salem- Kallakurachi, new broad-gauge Railway line during year 2006;

(b) if so, the details thereof, and the present status of the project;

(c) the reasons for delay in execution of the project; and

(d) time by which work on this project is likely to be started?

Answer given by the minister


MINISTER OF STATE IN THE MINISTRY OF RAILWAYS (SHRI K. H. MUNIYAPPA)

(a): Yes, Madam.

(b) & (c): Chinna Salem-Kallakkurichi new line work was sanctioned at a total cost of Rs. 38.91 crore. Delay in execution is on account of non-finalisation of alignment of this line due to number of representations from various quarters.

(d): Work will be started after finalisation of alignment and availability of land.