MINISTER OF STATE IN THE MINISTRY COAL (DR. DASARI NARAYANA RAO)
(a)to(d): Rashtriya Sahara in its edition dated July
28,2007 reported shutdown of NALCOâs Captive Power Plant
due to shortage of coal. Allocation of coal vis-Ã -vis
despatch of coal to NALCO, Angul Plant is given in the
table below:-
(figures in `000 tonnes)
Period Allocation Supply Materialization
April-June,07 1179.12 1193.47 101.21%
July,07 393.04 353.80 90.02%
April- 1572.15 1547.27 98.41%
July,2007
The linkage materialization was 98.4% of allocation.
Supply of coal to NALCO was made in accordance with
allocation made during the 1st Quarter of the current
year. However, during the month of July,2007 the supply
of coal was affected marginally due to transport
constraints arising out of law and order problems. Supply
was also affected due to inadequate availability of
railway wagons and due to non working of surface miner
at Bharatpur Mines. However, adequate arrangement has been
made for supply of coal to NALCO from other sources as a
short term measure to tide over the present situation.