THE MINISTER OF STATE (INDEPENDENT CHARGE) OF THE MINISTRY OF POWER
( SHRI JYOTIRADITYA M. SCINDIA )
(a) : Yes, Madam. The per capita electricity consumption of Arunachal
Pradesh for the year 2010-11 was 582.08 kWh as against national per capita
average of 818.75 kWh.
(b) : The year-wise target set and achievement thereof in the field of
hydro power generation in Arunachal Pradesh during the last five years and
upto 30.11.2012 is as per AnnexâI.
(c) : The major reasons for delay in setting up of hydro-electric
projects are delays in getting statutory clearances include inter-alia,
Environment & Forest Clearances, land acquisition problems, resettlement &
rehabilitation problems, law & order problems, geological surprises during the
construction phase etc.
The measures taken by Ministry of Power for post clearance
monitoring of the Hydro-Electric Projects are:-
(i) Central Electricity Authority (CEA) is monitoring the power
projects in pursuance of Section 73(f) of Electricity Act, 2003. The
progress of each project is monitored continuously through frequent site
visits, interaction with the developers, critical study of monthly progress
reports. Chairperson, CEA holds review meetings with the developers
and other stakeholders to sort out the critical issues.
(ii) A Power Project Monitoring Panel (PPMP) has been set up by the
Ministry of Power to independently follow up and monitor the progress of
the Hydro Projects.
(iii) Review meetings are taken by Ministry of Power regularly with the
concerned officers of CEA, equipment manufacturers, State Utilities/
CPSUs/Project developers, etc. to sort out the critical issues.
(d) : At present three hydro-electric projects are under construction in
Arunachal Pradesh, which, after completion would add 2710 MW capacity. The
details of these projects along with likely completion schedule and reasons for
delay are given in Annex-II.