Question : NBCC PROJECTS



(a) whether the National Building Construction Company (NBCC) has been awarded any contract for border fencing, housing complex and other major works during the last three years;

(b) if so, the details thereof and the present status of the above works, project-wise; and

(c) the time by which these projects are likely to be completed?

Answer given by the minister


MINISTER OF URBAN DEVELOPMENT AND CULTURE ( SHRI S. JAIPAL REDDY )

(a): Yes, Sir.

(b)&(c): Details of projects and time schedule alongwith the present status of projects secured by NBCC during the last three years is enclosed vide Annexures I, II and III.

ANNEXURES REFERRED TO IN REPLY TO PARTS (b)&(c) OF LOK SABHA USQ NO. 4217 FOR 21.12.2005.

ANNEXURE-I

BORDER FENCING WORKS SECURED BY NBCC

(2003-04 TO 2005-06 UPTO 30TH NOVEMBER`05)

 (Rs. lacs)
Sl. Name of Project Contractual Present Status Likely date No. Value of completion
1. Border Fencing works, 40681.00 Work in progress. 31.03.2006 Tripura 83% work completed.
2. Border Fencing works, 35978.41 Work in progress. 31.12.2006 Rann of Kutch, Gujarat 20% work completed.
3. Border Fencing works, 31796.93 Work in progress. 31.12.2006 Meghalaya 24% work completed.
4. Border Fencing Works, 12501.46 Work in progress. 31.12.2006 Mizoram 29.5% work completed.
5. Border Fencing works, 5816.33 Work in progress. 31.12.2006 Assam 20% work completed.

ANNEXURE-II
Housing Complex secured by NBCC - (2003-04 to 2005-06 upto 30th November`05)

Sl. Name of Project Contractual Present Status Likely date No. Value of completion
1. Defence Housin 4592.00 Work in progress. 31.12.2007 Project, Jodhpur (Air 38% work completed. Force)
2. Defence Housing 1060.00 Work in progress. 30.09.2007 Project, Jodhpur (Army) 1% work completed.
3. Defence Housing 6506.00 Work in progress. 31.03.2007 Project, Jaipur (Army) 31% work completed.
4. Defence Housing 4648.00 Work in progress. 31.08.2007 Project, Jaisalmer 3% work completed. (Army)
5. Defence Housing 1765.00 Work in progress. 31.08.2007 Project, Ambala (Air 17% work completed. Force)
6. Defence Housing 5353.00 Work in progress. 31.08.2006 Project, Vadodara (Air 34.5% work completed. Force)
7. Defence Housing 6850.00 Work in progress. 13.07.2007 Project, Deolali (Air 13% work completed. Force)

Major Works Secured by NBCC - Year Wise (2003-04 to 2005-06 upto November`05)

Sl. Name of Project Contractual Present Status Likely date No. Value of completion
1. 270 Cusec Pipeline Works 12000.00 Completed. from Murad Nagar to Sonia Vihar
2. Elevated Metro Track 13600.00 Completed. from Panchkuiyan Road to Kirti Nagar for DMRC (IJM - NBCC - VRM Joint Venture)
3. Construction of Civil 16220.04 Work in progress. 15.7.2007 Structural and 30% work completed. Architectural work of Main Power House Transformer Yard at Korba (East) 2 x 250 MW Chattisgarh
4. Construction of Civil, 12978.00 Work in progress. 15.7.2007 Structural and 18.3% work completed. Architectural of Unit 7 & 8 (2 x 250 MW) of Chandrapura TPS, DVC, Jharkhand
5. Bodoland Hospital and 4190.00 Work just started. 31.7.2007 Nursing College at 6% work completed. Kokrihat in Assam
6. Construction of Coal 4762.00 Work in progress. 31.7.2007 Handling and Ash 11.5% work completed. Handling Plant at Chandrapura TPS Unit 7&8 at Jharkhand
7. Supply of Pre-fabricated 5924.00 Work just started. 31.12.2006 Super Structure of CRC and IARH at Imphal for Manipur Sericulture Project
8. Construction of Nagaland 4300.00 Work in progress. 31.1.2007 University at Nagaland 18% work completed.
9. Construction of Rural 23661.00 Work in progress. 31.3.2008 Roads in West Tripura 10% work completed. District under Pradhan Mantri Gram Sadak Yojana (PMGSY) - Tripura

Sl. Name of Project Contractual Present Status Likely date No. Value of completion
10. Construction of Rural 26625.00 Work in progress. 30.9.2006 Roads under Pradhan 17% work completed. Mantri Gram Sadak Yojana (PMGSY) - Bihar
11. Site leveling work 11800.00 Work in progress. 31.3.2006 package for Barh Super 75% work completed. Thermal Power Project, Bihar