MINISTER OF URBAN DEVELOPMENT AND CULTURE ( SHRI S. JAIPAL REDDY )
(a): Yes, Sir.
(b)&(c): Details of projects and time schedule alongwith the
present status of projects secured by NBCC during the last three
years is enclosed vide Annexures I, II and III.
ANNEXURES REFERRED TO IN REPLY TO PARTS (b)&(c) OF LOK SABHA USQ NO. 4217 FOR
21.12.2005.
ANNEXURE-I
BORDER FENCING WORKS SECURED BY NBCC
(2003-04 TO 2005-06 UPTO 30TH NOVEMBER`05)
(Rs. lacs)
Sl. Name of Project Contractual Present Status Likely date
No. Value of completion
1. Border Fencing works, 40681.00 Work in progress. 31.03.2006
Tripura 83% work completed.
2. Border Fencing works, 35978.41 Work in progress. 31.12.2006
Rann of Kutch, Gujarat 20% work completed.
3. Border Fencing works, 31796.93 Work in progress. 31.12.2006
Meghalaya 24% work completed.
4. Border Fencing Works, 12501.46 Work in progress. 31.12.2006
Mizoram 29.5% work completed.
5. Border Fencing works, 5816.33 Work in progress. 31.12.2006
Assam 20% work completed.
ANNEXURE-II
Housing Complex secured by NBCC - (2003-04 to 2005-06 upto 30th November`05)
Sl. Name of Project Contractual Present Status Likely date
No. Value of completion
1. Defence Housin 4592.00 Work in progress. 31.12.2007
Project, Jodhpur (Air 38% work completed.
Force)
2. Defence Housing 1060.00 Work in progress. 30.09.2007
Project, Jodhpur (Army) 1% work completed.
3. Defence Housing 6506.00 Work in progress. 31.03.2007
Project, Jaipur (Army) 31% work completed.
4. Defence Housing 4648.00 Work in progress. 31.08.2007
Project, Jaisalmer 3% work completed.
(Army)
5. Defence Housing 1765.00 Work in progress. 31.08.2007
Project, Ambala (Air 17% work completed.
Force)
6. Defence Housing 5353.00 Work in progress. 31.08.2006
Project, Vadodara (Air 34.5% work completed.
Force)
7. Defence Housing 6850.00 Work in progress. 13.07.2007
Project, Deolali (Air 13% work completed.
Force)
Major Works Secured by NBCC - Year Wise (2003-04 to 2005-06 upto November`05)
Sl. Name of Project Contractual Present Status Likely date
No. Value of completion
1. 270 Cusec Pipeline Works 12000.00 Completed.
from Murad Nagar to
Sonia Vihar
2. Elevated Metro Track 13600.00 Completed.
from Panchkuiyan Road to
Kirti Nagar for DMRC
(IJM - NBCC - VRM Joint
Venture)
3. Construction of Civil 16220.04 Work in progress. 15.7.2007
Structural and 30% work completed.
Architectural work of
Main Power House
Transformer Yard at
Korba (East) 2 x 250 MW
Chattisgarh
4. Construction of Civil, 12978.00 Work in progress. 15.7.2007
Structural and 18.3% work completed.
Architectural of Unit 7
& 8 (2 x 250 MW) of
Chandrapura TPS, DVC,
Jharkhand
5. Bodoland Hospital and 4190.00 Work just started. 31.7.2007
Nursing College at 6% work completed.
Kokrihat in Assam
6. Construction of Coal 4762.00 Work in progress. 31.7.2007
Handling and Ash 11.5% work completed.
Handling Plant at
Chandrapura TPS Unit 7&8
at Jharkhand
7. Supply of Pre-fabricated 5924.00 Work just started. 31.12.2006
Super Structure of CRC
and IARH at Imphal for
Manipur Sericulture
Project
8. Construction of Nagaland 4300.00 Work in progress. 31.1.2007
University at Nagaland 18% work completed.
9. Construction of Rural 23661.00 Work in progress. 31.3.2008
Roads in West Tripura 10% work completed.
District under Pradhan
Mantri Gram Sadak Yojana
(PMGSY) - Tripura
Sl. Name of Project Contractual Present Status Likely date
No. Value of completion
10. Construction of Rural 26625.00 Work in progress. 30.9.2006
Roads under Pradhan 17% work completed.
Mantri Gram Sadak Yojana
(PMGSY) - Bihar
11. Site leveling work 11800.00 Work in progress. 31.3.2006
package for Barh Super 75% work completed.
Thermal Power Project,
Bihar