MINISTER OF STATE IN THE MINISTRY OF RAILWAYS (SHRI KOTLA JAYA SURYA PRAKASH REDDY )
(a) to (c): A Statement is laid on the Table of the House.
STATEMENT REFERRED TO IN REPLY TO PARTS (a) TO (c) OF UNSTARRED QUESTION NO.1802 BY SHRI
HUKUMDEV NARAYAN YADAV TO BE ANSWERED IN LOK SABHA ON 07.03.2013 REGARDING RAILWAY LINES
(a): The status of the projects is as under:-.
(i) Sakri-Nirmali-Bhaptiyahi is part of Sakri-Nirmali-Laukahabazar-Saharsa-Forbesganj gauge
conversion project for which earthwork and bridgework has been taken up in entire section.
In this section, bridge across Kosi river taken up as new line project is also in advance stage of execution.
(ii) Sitamarhi-Jaynagar-Nirmali via Susand new line (188.9 km):- Estimate sanctioned.
Funds deposited to concerned District Administration, Sitamarhi for acquisition of land.
Preliminary work taken up.
(iii) Darbhanga-Muzaffarpur new line (56 km):- Final location survey completed. Work in
preliminary stages.
(iv) Madhubani-Benipatti-Pupri new line (50 km):- Survey has been taken up.
At present, there is no proposal for construction of Hariharpur halt on Darbhanga-Sitamarhi
section.
(b): Due to limited availability of resources, difficulty in land acquisition, etc.
on-going projects get delayed. Railways have a huge throwforward of Rs.1.47 lakh crore
for ongoing New Lines, Gauge Conversion and Doubling projects with limited amount of
resources resulting in thin spread of funds which are allocated annually to these projects
as per availability of resources.
(c ): To expedite completion of projects, forestry and other clearances have been taken
up at highest level. Regular coordination meetings are held with State Governments for
providing adequate security at work sites. Empowerment of field units have also been
taken up to expedite completion of projects.