THE MINISTER OF ROAD TRANSPORT AND HIGHWAYS (SHRI KAMAL NATH)
(a): 99.2% of Golden Quadrilateral (GQ) is complete. Out of the total length of 7142 km
of North South and East West (NS-EW) Corridors, 4 laning has been completed in 5258 km, and
work in 1457 km is under progress. The four-laning work in the remaining 427 km is yet to
be awarded.
(b) to (f): A Statement is laid on the Table of the House.
STATEMENT REFERRED TO IN REPLY TO PARTS (b) TO (f) OF LOK SABHA STARRED QUESTION NO.109 FOR
ANSWER ON 16TH NOVEMBER, 2010 ASKED BY SHRI HUKUMDEV NARAYAN YADAV AND SHRI BHOOPENDRA SINGH
REGARDING CONSTRUCTION OF NS & EW CORRIDOR AND GQ
(b): The projects were delayed due to various reasons like, delay in obtaining forest/
environmental clearances, clearances for ROBs, land acquisition and utility shifting, poor
performance by contractors, floods and poor law & order condition in some States, etc.
(c): The name of construction companies is enclosed as Annex I.
(d) & (e): Details are given in Annex II.
(f): Where the delay was due to reasons attributable to the Contractor, show cause notices
were issued by NHAI for placing the Contractor/firm in the list of non performers; and 25 firms
were placed in the list of non-performers and 21 contracts were terminated and their performance
bank guarantees were encashed and plant & machinery were confiscated in the terminated contracts.