(a) the progress of construction of building Central
Schools in Ladakh;
(b) the funds allocated/released for construction work of
each school, school-wise; and
(c) the expected time of completion of construction work of
each school?
(a) the progress of construction of building Central
Schools in Ladakh;
(b) the funds allocated/released for construction work of
each school, school-wise; and
(c) the expected time of completion of construction work of
each school?
MINISTER OF STATE IN THE MINISTRY OF HUMAN RESOURCE DEVELOPMENT
(DR. D. PURANDESWARI)
(a) There are 3 Kendriya Vidyalayas (KVs) in Ladakh at Leh,
Kargil and Nubra. The schools building at Leh has already
been constructed during the year 2000. The present status
for KV, Kargil and KV, Nubra is as follows:-
(i) KV, Kargil: CPWD has been approached for submission of
drawings and estimates. These have not been submitted
as yet.
(ii) KV, Nubra: Land has been accepted from State
Government on 15.4.2011. Formalities for transfer are
yet to be completed. But meanwhile, planning has been
initiated for construction of school building. CPWD has
been approached for drawings and estimates.
(b) No funds have been allocated / released for KV, Kargil
& KV Nubra as the construction activities have not
commenced.
(c) Construction of school buildings is a continuous
process and depends upon transfer of suitable plot of land
by sponsoring agency, submission of plan & estimate by the
construction agency and availability of budget allocation
under Plan Head. Generally 2 to 3 years time is required for
completion of building in normal conditions after sanctions.