Question : DOUBLING OF RAIL LINES



(a) the target fixed for doubling of railway lines during the Ninth Five Year Plan;

(b) whether the target fixed for has been achieved during the said period;

(c) if not, the reasons therefor;

(d) the details of railway lines doubled during the said period; and

(e) the amount spent so far for achieving the aforesaid target?

Answer given by the minister

THE MINISTER OF STATE IN THE MINISTRY OF RAILWAYS (SHRI DIGVIJAY SINGH)

(a): The target of doubling of 2500 km was fixed for the 9th five year plan.

(b): The progress achieved so far in first four years of the 9th plan is 840 km. During the last year (2001-2002) of 9th plan, 300 km of doubling is targeted for completion.

(c): The performance during IXth Plan is expected to be less as compared to the target fixed for the Plan due to constraint of resources and technical constraints, contractor failures etc.

(d): The details of railway lines doubled during the first four years of the 9th Plan are given as under:-

Railway	Section	KM
Central Diva-Panvel 26 Central Diva-Vasai(Vasai-Bhiwandi) 28 Central Hetampur-Gher 1 Central Katni-Katni ‘A’ Cabin 3 Central Daund-Bigwan 28 Central Nishatpura ‘A’ &’D’ Cabins 1 Central Sevagram-Chitoda 4 Eastern Khana-Sainthia (Ph.I) (Khana-Jhaptardal) 6 Eastern Khana-Sainthia Ph.II (Jhaptardhal Guskara) 16 Eastern 3rd line Dehri-on-Sone-Mughal Sarai 94 Eastern Sahibganj-New Farakka-Malda Town 37 Eastern Khana-Sainthia (Phase-III) (Bolpur-Bedia) 20 Eastern Chandanpur-Belmuri 5 Eastern Patna-Parsa Bazar 7 NE Railway Gonda-Maizapur 11 NE Railway Kanki-Dalkola 14 Northern Ghaziabad-Hapur 43 Northern Moradnagar-Meerut 30 South Central Rukmapur-Vikarabad (Wadi-Vikarabad section) 30 South Central Solapur-Hottgi 15 South Eastern Saragbundia-Korba 20 South Eastern 3rd line of Akaltara-Naila-Hasdeo(Part of Akaltara-Champa) 39 South Eastern Gajapatinagaram-Vizainagaram 22 South Eastern Rajathgarh-Selegaon (partly) 4 South Eastern Raghunathpur-Rahama (Part) 16 Western Kota-Gurla Chambal Bridge 1 South Eastern Balpur-Kothari Rd.-Saragbundia 15 Southern Eastern Raipur-Sarona 11 Southern Eastern Sarona-Bhilai 11 Southern Shoranur-Mangalore 185 Southern Quilon-Trivandrum 50 Southern Malur-Bangarapet 27 Western Bolai-Kalisindh 8 Western Bercha-Kalisindh 12
Total 840 Km.


(e): The amount spent on doubling works during first 3 years of the IX th plan is Rs.1292.53 crores. For the fourth year (2000-2001), the actual expenditure would be known after finalization of accounts by June’2001.