THE MINISTER OF STATE IN THE MINISTRY OF ROAD TRANSPORT AND HIGHWAYS (SHRI R.P.N. SINGH)
(a) & (b) Yes Sir. Â 131 projects have been delayed mainly due to problems associated
with land acquisition, shifting of utilities, obtaining environment and forest clearance,
approval for Road Over Bridges, poor performance of some contractors due to cash flow
constraints and other reasons, law and order problems in some states etc. The award of
projects through Build, Operate Transfer (BOT) Toll/Annuity mode under Public Private
Partnership was affected due to the recent downturn in the economy which affected the ability
of private investors/developers to raise necessary finance for projects.