Question : DREDGING WORK UNDER SETHUSAMUNDRAM PROJECT



(a) whether the dredging companies were assigned the job of dredging under Sethusamundram scheme in Rameshwaram alongwith the details of the said companies;

(b)     the company-wise details of the amount paid;

(c)     the basis for assigning the dredging work; and

(d)     the company-wise details of owners and managing directors?

Answer given by the minister


MINISTER OF SHIPPING (SHRI G. K. VASAN)

(a) & (b): The dredging work for the Sethusamudram Project including the dredging work in Adam’s Bridge Area near Rameswaram was assigned only to M/s Dredging Corporation of India (DCI) for which a sum of Rs.699.12 crores as on date has been paid.

(c) & (d): The dredging work of the Sethusamudram Project has been assigned to M/s Dredging Corporation of India being a Government of India Undertaking and its Managing Director is Captain S.S. Tripathi.