Question : RAILWAY LINE BETWEEN LOHARDAGA TO KORBA



(a) whether the work on new railway line between Lohardaga and Tori is going on at a very slow pace;

(b) if so, the reasons therefor;

(c) the time by which the said work is likely to be completed;

(d) whether the Railways proposes to lay a new railway line on Lohardaga-Gumla-Jaspur-Korba route; and

(e) if so, the details thereof?

Answer given by the minister


MINISTER OF STATE IN THE MINISTRY OF RAILWAYS (SHRI K.H. MUNIYAPPA)

(a) & (b): The work is being progressed as per availability of resources. There has been some delay due to adverse law and order conditions in the area.

(c): Lohardaga-Bakrichampi (14.5Km) portion of the work is targeted for completion during 2009-10. Target date of completion of the remaining portion has not yet been fixed.

(d) & (e): No Madam. Survey for Lohardaga-Korba new line was completed in 2003-04 and the proposed new line was not taken up.