(a) whether the Government has a plan for doubling the railway line between Delhi and Saharanpur via Muzaffar Nagar;
(b) if so, the details thereof; and
(c) the time by which this work is likely to be started?
(a) whether the Government has a plan for doubling the railway line between Delhi and Saharanpur via Muzaffar Nagar;
(b) if so, the details thereof; and
(c) the time by which this work is likely to be started?
MINISTER OF STATE IN THE MINISTRY OF RAILWAYS ( SHRI R. VELU )
(a) & (b) : Double line between Delhi-Meerut already exists. An updating
Survey for Meerut-Saharanpur doubling (114 kms) has been taken up in 2004-05.
Further decision to do the doubling of the remaining section shall depend
on the results of the survey.
(c): The project is not yet sanctioned.