THE MINISTER OF STATE FOR SCIENCE & TECHNOLOGY AND EARTH SCIENCES (INDEPENDENT CHARGES), PMO,
PERSONNEL, PUBLIC GRIEVANCES AND PENSIONS AND PARLIAMENTARY AFFAIRS(SHRI PRITHVIRAJ CHAVAN)
(a)to(c) RAPS-1 was the first Pressurised Heavy Water Reactor which started commercial operation
in the year 1973. The unit has been shut down from October, 2004 for techno-economic evaluation
on its refurbishment/continuation of operations.
Feeder Replacement work on RAPS-2 (200 MWe) has been completed and the unit is now awaiting fuel
loading. The fuel fabrication has also commenced at Nuclear Fuel Complex, Hyderabad and the
operation of this unit is expected to commence from September, 2009.
(d) Rajasthan has been allocated power from other central generating stations including
nuclear power reactors at RAPP-3 & 4 and NAPS - 1 &2. In addition, construction works on
RAPP-5&6 ( 2 x 220 MWe) also at Rawatbhata, Rajasthan have been completed and operation
is expected to commence in year 2009.