Question : Madurai Smart City Projects

(a) the status of overall work in progress for Madurai Smart City Projects, project-wise; and

(b) the time-line by which Madurai Smart City Projects will be completed?

Answer given by the minister

(a) Madurai was selected to be developed as Smart City in Round-2 of Smart Cities selection process on 20th September, 2016. So far, out of 14 projects worth Rs.977.55 Crore, Madurai Smart City has issued work order in all the projects of which 1 project worth Rs.12 Crore has been completed. The present status of these projects is given in Annexure-I.

(b) Madurai Smart City is expected to complete its projects within 5 years from the date of selection.

*****



Download PDF Files