MINISTER OF THE STATE IN THE MINISTRY OF COAL (DR. DASARI NARAYANA RAO)
(a) & (b): No, Sir. The services of only 2017 employees
of all categories including SC, ST & OBC were terminated due
to proved misconduct of long absenteeism in these three
companies as detailed below:-
Year Central Eastern Bharat Total Coalfields Coalfield Coking Limited Limited Coal Limited
2004-05 156 310 413 879
2005-06 101 174 308 583
2006-07 74 130 351 555
Total 331 614 1072 2017
(c): No. Sir. The certified Standing Orders applicable for the
workmen, inter-alia, has provisions for the terminated
employees to make appeal to the Appellate Authority. Such
appeals, as and when received, are considered on merit by
the Appellate Authority. Reinstatement is made only on the
basis of the decision of the Appellate Authority on the
merit of the individual case. The prescribed procedure for
reinstatement of workers is being followed by Coal India
Limited and its Subsidiary Companies.
(d)& e): Number of employees reinstated Company-wise is given
below :-
Company 2004-05 2005-06 2006-07
Eastern Coalfields 24 22 22
Limited
Bharat Coking Coal 72 32 59
Limited
Central Coalfields 02 02 07
Limited
Western Coalfields 07 06 06
Limited
South Eastern 32 27 65
Coalfields Limited
Mahanadi Coalfields - - 04
Limited
Total 137 89 163