Question : Survey of Abu Road and Ambaji Road Rail Line

(a) whether approval has been given to connect Abu Road and Ambaji Road with a railway line in the Railway Budget of 2017 and if so, the details thereof;

(b) the total length of this railway line and the estimated cost of this project;

(c) whether any time limit has been fixed to start the work from survey to construction of the said railway line; and

(d) if so, the details thereof?

Answer given by the minister

MINISTER OF RAILWAYS AND COMMERCE & INDUSTRY
(SHRI PIYUSH GOYAL)
(a) to (d): Taranga Hill-Abu Road via Ambaji new line project has been included in the Budget 2017-18 subject to requisite approvals. Final Location Survey (FLS) has been taken up. After this, further decision shall be taken up.
*****