THE MINISTER OF HOUSING AND URBAN POVERTY ALLEVIATION (SHRI AJAY MAKEN)
(a): As reported by CGEWHO, housing schemes under the organization to provide houses
to Central Government Employees in different parts of the country are as under: -
Housing projects where Housing projects under planning are:
construction is in
progress are:
i. Chennai (Ph-II); i. Vishakapatnam;
ii. Mohali (Ph-I); ii. Meerut (Ph-II);
iii. Bhubaneswar (Ph-I); iii. Greater Noida;
iv. Meerut (Ph-I); iv. Chennai (Ph-III);
v. Kolkata(Ph-II); v. Mohali (SAS Nagar)
vi. Bhubaneswar(Ph-II);
vii. Mohali (Ph-II)
(b)&(c): As reported by CGEWHO schemes are planned after conducting a demand survey and
thereafter making attempts to acquire land from State Government Authorities. In case
of non-availability of land from State Government Authorities, housing schemes are planned
as turnkey projects wherein land is also provided by the construction agency. Hence no
definite time frame can be planned for such housing schemes. Allotment of houses under
each Scheme is made to eligible applicants after the draw. The specific allocation of
dwelling unit number in a particular project is made at the time of the completion of
the project. Allotment has been made in the following housing schemes:
Schemes Time Schedule
i. Chennai (Ph-II); Within three months
ii. Mohali (Ph-I); after formal closure
iii. Bhubaneswar (Ph-I); of the scheme,
iv. Meerut (Ph-I); allotment has been
v. Kolkata (Ph-II); made in all the
vi. Bhubaneswar (Ph-II); and schemes.
vii. Mohali (Ph-II);
(d): CGEWHO housing schemes are initially planned with an anticipation of getting the
processes completed as per estimates and plan. However,priorpermission has to be obtained
from statutory municipal and development authoritiesand No Objection Certificates from
related state departments like fire, airport, environment etc. before commencement of
construction. Even after the completion of the works, the requisite completion/occupancy
certificate from the statutory authorities and subsequent service connections viz.
electricity, water, sewage etc. also get delayed which are beyond the control of CGEWHO.