Question : Marhowra and Madhepura Rail Projects

(a) whether the railways has made both its Marhowra and Madhepura rail projects fully operational;

(b) if so, the details thereof and the cost of both these projects;

(c) the rail line stretches where electrification work is being executed in Bihar along with the time by which the said work is likely to be completed;

(d) the time by which extension work of Danapur yard is likely to be completed;

(e) whether the people residing in Jamaluddin Chok village are facing inconvenience in water drainage due to expansion of Danapur yard;

(f) if so, the details thereof; and

(g) the measures being taken to address the above mentioned problem of people residing in Jamaluddin Chok village?

Answer given by the minister

MINISTER OF STATE IN THE MINISTRY OF RAILWAYS

(SHRI RAJEN GOHAIN)

(a) to (g) A Statement is laid on the Table of the House.
*****