MINISTER OF STATE IN THE MINISTRY OF RAILWAYS (SHRI DIGVIJAY SINGH)
(a) to (h): A statement is attached.
STATEMENT REFERRED TO IN REPLY TO PARTS (a) TO (h) OF LOK
SABHA UNSTARRED QUESTION NO. 5015 BY SHRI ASHOK N. MOHOL,
SHRI VIJAY GOEL AND SHRI JAI PRAKASH TO BE ANSWERED ON
19.4.2001 REGARDING TRIAL OF IMPORTED COACHES.
(a) Yes, Sir.
(b) The amount of foreign exchange incurred on import of
24 coaches from Germany is DM 52,663,500.
(c) The ALSTOM-LHB coaches undergoing trials in Northern
Railway were damaged due to stone throwing incidences.
However, the incidences did not take place on 4th March
2001 but on 3rd , 6th, 13th & 14th March 2001.
(d) The estimated loss suffered is approximately Rs. 2.8
lakh.
(e) The coaches were stoned by miscreants and therefore
no enquiry was found necessary to find out the reasons.
(f) Does not arise.
(g) Yes, Sir. The Railways have entered into a Transfer
of Technology contract with M/S ALSTOM-LHB, Germany in
order to transfer the complete know-how for manufacture
of 2nd class AC chair car, executive class chair car and
generator-cum-brake van which were imported. The contract
also covers complete design development and manufacturing
of prototype of following 3 types of coaches:
(i) Air conditioned first class-cum-
sleeper coach.
(ii) Air-conditioned sleeper coach.
(iii) Air-conditioned hot buffet coach.
The contract also covers development of vendors for
indigenous supply of components by suitable
collaborations wherever necessary.
(h) It is proposed to manufacture 27 coaches during the
year 2001-02. Number of coaches to be manufactured during
subsequent years will be decided based on the requirement
and availability of funds.