Question : SURVEY OF HARIHAR TO MAHARASHTRA FOUR LANING PROJECT



(a) whether the Government propose to undertake survey of road from Harihar to Maharashtra for taking up for laning work ;

(b) if so, whether the survey work has been entrusted;

(c) if so, the details thereof;

(d) whether the project report has been submitted to the National Highways Authority of India; and

(e) if not, the time by which the report is expected to be submitted?

Answer given by the minister


MINISTER OF STATE IN THE MINISTRY OF SURFACE TRANSPORT

(DR. DEBENDRA PRADHAN)

(a) & (b) Yes, Sir.

(c) The work is being done in following packages:

i) Harihar - Havari (km. 282-340) length of 58 kms.
ii) Belgaum bypass ( km. 495-515) length of 20 kms.
iii) Harihar - Maharashtra border excluding Belgaum bypass & Hubli-Dharwad bypass (km. 340-592) length of 202 kms.

(d) to (e) The detailed project report for various sections are targetted to be received by the end of year 2000.