MINISTER OF STATE IN THE MINISTRY OF STEEL ( DR. AKHILESH DAS )
(a)&(b) Both the major steel-making companies under the administrative control of the
Ministry of Steel, i.e. the Steel Authority of India Ltd.(SAIL) and Rashtriya Ispat Nigam
Ltd.(RINL) are undertaking ambitious modernization and expansion plans. SAIL proposes to
modernize and expand capacity at its plants to increase production of hot metal from present
level of 14.6 million tonnes per annum (2006-07) to 26 million tonnes per annum by the year
2010-11 and the expansion plan will be completed by 2010 progressively. The Rashtriya Ispat
Nigam Ltd. (RINL) proposes to expand its capacity to increase production of hot metal from
the present level of 4.05 million tonnes per annum (2006-07) to 6.50 million tonnes per annum
by the year 2009-10 and the expansion plan is expected to be completed by March, 2010.
M/o Steel does not monitor and maintain the details and status of projects for modernization
in the private sector.
(c) As on date, SAIL has approved the expansion/substance schemes of all major steel
plants at a present indicative cost of about Rs.49,000 Crores. Plant-wise details of the
same is as under:
(Rs. in crores)
SAIL Total Investment
IISCO Steel Plant (ISP) 8871
Durgapur Steel Plant (DSP) 5549
Rourkela Steel Plant (RSP) 7668
Bokaro Steel Plant (BSL) 8399
Bhilai Steel Plant (BSP) 11262
Salem Steel Plant (SSP) 1419
Sustenance Scheme 6065
Total 49233
The anticipated cost of expansion of Rashtriya Ispat Nigam Limited (RINL) taking into
consideration the packages/items ordered and the balance works out to Rs.11,200 Crores.
(d) For meeting the requirements of enhanced production, SAIL will be increasing its
labour productivity through efficient operations and higher levels of automation. There would
be requirement for recruitments in project area to meet the work load in expansion projects.
However, there would be progressive reduction in number of employees in the works and non-
works areas due to yearly separation. Selective recruitment will also be undertaken for
recouping separations and improving the age mix of the work force. Requirement of expansion
projects shall also be met partially through retraining and redeployment of existing employees.
The total requirement of capital machinery for expansion of SAIL are yet to be
finalized as tendering activity for various packages of expansion plans are in progress.
365 Acres of additional land is required only for expansion of IISCO Steel Plant (ISP)
of SAIL and no additional land is required for expansion of others Steel Plants of SAIL.
As per project report submitted by the consultant for the expansion of RINL, the
estimated requirement of additional manpower is 1995, the estimated capital machinery cost
is Rs.7424 Crores and the estimated requirement of land is 750 Acres within the existing
plant boundary wall.